When will staff be working?
Work will be undertaken across 30 day shifts and 6 night shifts between Wednesday 3 September and Sunday 19 October 2025, weather permitting.
Day work hours will be between Monday and Friday, 7am to 6pm.
Night work hours will be between Sunday and Thursday, 8pm and 5am, the next day.
Work will be paused on Friday nights, Saturdays or when there are planned major events at Sydney Olympic Park and Monday 6 October public holiday.
What will this mean for you and how it will be managed?
Some of the work needs to be carried out at night to minimise disruption to traffic and reduce safety risks to our workers, pedestrians and motorists.
It may be noisy at times, but impact will be minimised by:
- turning off equipment and vehicles when not in use
- completing noisier tasks by midnight
- using quieter equipment where possible.
Traffic changes
There will be temporary traffic changes to make sure the work zone is safe. These changes could include lane closures and a reduced speed limit of 40km/h.
Pedestrian access will be maintained under the guidance of traffic controllers. Please keep to speed limits and follow the direction of traffic controllers and signs.
For the latest traffic updates, you can call 132 701, visit livetraffic.com or download the Live Traffic NSW App.
Transport for NSW thanks the community for their patience while we complete this important work.
|