Strathfield to Enfield Dean Reserve Works

Monday, 20th August, 2018

A new zone substation will be built in Dunlop Street, Strathfield South, to replace existing zone substation in Hillcrest Avenue, Enfield. 

New cables will be installed in local streets between Enfield and Strathfield South. Cables will run from the back of the substation site in Dunlop street into Dean Reserve, through the Dean Reserve carpark and into Dean Street. Please see attached map. 

Works in Dean Reserve are expected to start on 27 August 2018 for three weeks between the hours 7am - 6pm Mondays to Fridays; 8am - 1pm on Saturdays

Please see below attachment for further information. 

 

Back